Elements of complexity

  • Design work included that of a 600 m long, under pressure tunnel with a steel liner on the lower section.
  • Supply and accessibility problems during the construction involving an impact on the project costs and requiring a design optimization.

PROJECT DESCRIPTION

The Sheldrake hydroelectric installation has a 25 MW power capacity and is located on the Sheldrake river in the town of Rivière-au-Tonnerre in Minganie, near Baie-Comeau (Québec). The project consists of building a concrete dam-bridge, a spillway, a cofferdam, the water intake, a pressure tunnel with a steel liner and the power plant.

HYDROSYS’ RESPONSABILITIES

Detailed engineering including a maximization of technical solutions as well as assisting AXOR during every step of the project, aided in the hydro power project’s development.

SERVICES RENDERED

  • Supervision of the geotechnical investigation.
  • Techno-economical optimization studies.
  • Structural stability assessment.
  • Governmental authorization applications.
  • Tunnel and tunnel liner engineering.
  • Detailed drawings and specifications for every component of the facility.
  • Drawings and specifications for the construction of the dam, the spillway, the cofferdam, the water intake, the headrace, the tunnel and the main embankment.
  • Engineering of the bridge for heavy trucks, engineering of the steel access pathway and of the other compensating measures.
  • Technical support during construction.